A driveway is three orders, not one. Size each lift on this page and you will not be short of base stone on the day the truck arrives.

Three liftsCost per yard or tonCompaction allowancePrint the list

Material calculator

Material
Gravel and stone
Area 1 · Rectangle

Beds, lawns, parking pads — anything with square corners.

3.11 cubic yards to buy 84 cu ft · 3.78 short tons · 168 bags of 0.5 cu ft
+154
Volume
84 ft³
Cubic yards
3.11 yd³
Cubic metres
2.38 m³
Weight
7,560 lb
Short tons
3.78
Metric tonnes
3.43 t

240 ft² of ground × 4 in average depth ÷ 12 = 80 ft³

80 ft³ × 90 lb/ft³ (#57 stone) = 7,560 lb

+5% waste → 3.11 yd³ to buy, 168 bags

Type a price above to see a material total.

Bulk density 90 lb/ft³, published range 85–95. Wet material weighs more; your supplier's figure wins.

Area by area (1)
#ShapeMeasurementsDepthAreaVolume
1 Rectangle 20 × 12 ft 4 in 240 ft² 80 ft³

Worked examples

Every number below is produced by the same engine that runs in the browser, at build time — so the examples cannot drift from the calculator above.

The same 20 × 12 ft drive, lift by lift — computed by this page's engine at build time
ScenarioMaterialVolumeCubic yardsShort tonsMetric tonnesBags
20 × 12 ft, 4 in of #3 bottom stone #3 crushed stone 80 ft³ 2.96 yd³ 3.6 3.27 160 bags of 0.5 cu ft
20 × 12 ft, 4 in of #57 middle course #57 crushed stone 80 ft³ 2.96 yd³ 3.6 3.27 160 bags of 0.5 cu ft
20 × 12 ft, 2 in of #411 surface #411 crushed stone 40 ft³ 1.48 yd³ 1.8 1.63 80 bags of 0.5 cu ft

Reference tables

Why one order is not enough

A gravel driveway that lasts is built from more than one size of stone, because each size does a different job. The bottom lift of large angular stone bridges soft ground and lets water move. The middle course of #57 knocks the sharp edges off that base and spreads the load. The surface course of a mixed size like #411 compacts into something firm enough to walk and drive on without swallowing a wheel.

The alternative — one thick layer of a single stone — works until the first wet spring, when the stone disappears into the subgrade and the drive turns into a rut with gravel at the edges.

What each lift does

The thickness question, answered honestly

There is no national specification for a private gravel driveway, and this page will not pretend otherwise. Thickness is set by your soil, how the site drains and what drives on it: a garden trailer needs less than a delivery truck, and clay holds a lift that sand will swallow. The 4-inch lift used as the default here is a common starting point, not a rule, and the surface course is usually thinner than the base.

What that means in practice: have the number in your head before you call, then ask the contractor or the quarry what they would put on your soil. They will have built the same drive a hundred times on your side of the county. The calculator's job is to turn whatever thickness they name into yards, tons and money.

Compaction deserves its own allowance. A lift that measures 4 inches after the plate compactor went over it started life at 5 or 6 inches. That is what the waste field is for on this page — 5 to 10% is the usual range, and a driveway is the job where it matters most.

Geotextile, drainage and the crown

A woven geotextile between the subgrade and the bottom lift stops soil pumping up into the stone and stone sinking into the soil. It is cheap relative to a load of stone and it is impossible to add later without taking the drive apart.

Water is what destroys gravel drives, so the surface needs somewhere to drain: a crown of an inch or two across the width, shoulders that fall away, and a ditch or a French drain on the uphill side if the ground around the drive sheds water onto it. A drive that holds water will hold ruts.

Edge containment matters as much on a drive as on a path. Without an edge, the surface course spreads outward under traffic and the crown flattens, which is the beginning of the end for drainage.

Costing it in the unit your supplier sells

Quarries quote by the ton more often than by the yard, and the two are not interchangeable: at the 90 lb/ft³ used for the crushed stones here, a cubic yard is 2,430 lb, or 1.22 short tons. A quote of "1.4 tons per yard" is the same stone described wetter or measured differently, which is why the cost field lets you price by the yard, by the ton or by the bag.

Delivery is usually priced per load with a minimum, and a 20 × 12 ft drive at three lifts is several loads. That is a line item the calculator cannot see, so add it yourself before comparing quotes. The page also leaves the price blank until you type one: a national average invented here would be wrong in your county and stale within a month.

Maintaining a gravel drive

The annual job is re-grading: drag a box blade or a rake down the drive to pull stone back from the edges into the wheel tracks, then re-compact. Spot the low places after a rain, because the puddles mark where the surface has thinned. A bag or two of the surface stone in the spring is cheaper than a load in July.

Weeds in a drive are a sign the surface has thinned or that fines have collected. Rake the loose material out, re-grade, and top up rather than spraying: bare stone at the right depth does not grow much.

Questions this page answers

How many tons of gravel do I need for a 20 × 12 ft driveway?

At 4 inches deep the drive is 240 square feet × 0.333 feet = 80 cubic feet, which is 2.96 cubic yards. In #57 stone at 90 lb/ft³ that weighs 7,200 lb, or 3.6 short tons, before any waste allowance. Add 5 to 10% for compaction and spillage.

Is 4 inches deep enough for a gravel driveway?

Four inches is a common single lift and a reasonable starting point, but it is not a specification and it is not enough over soft ground. Two lifts of 4 inches, or a bottom lift of #3 over geotextile and then #57, hold up far better. Ask a local contractor what your soil needs.

Do I need a geotextile under driveway gravel?

It is strongly advisable over soil, and it is the one part of the job you cannot add later. A woven fabric separates the subgrade from the stone so the two do not mix, which keeps the lift draining and keeps its thickness.

What is the difference between #57 and #411?

Both are crushed stone; #57 is a single washed size class, roughly 1 inch down to the No. 4 sieve, and it stays loose. #411 mixes stone with fines so it compacts into a firm surface. #57 is the middle course, #411 is usually the top.

How much extra should I order for compaction?

Five to ten percent is the usual allowance for a driveway lift, on top of the finished thickness you want. If the lift has to end up 4 inches thick after compaction, order enough for 4.5 to 5 inches and compact in two passes.

Quantity estimate only. Bulk density varies with moisture and gradation, compaction removes depth from a lift, and the depths quoted for playground surfacing come from CPSC Publication 325 for the material and fall height stated there. Check the CPSC handbook and your equipment manufacturer; this calculator does not certify safety. Nothing you type is uploaded.